FG Begins N366m Palliative Work On Abuja – Kaduna Dual Carriageway

By Alice Etuka, Abuja

The Federal Ministry of Works has commenced emergency repairs of failed portions of the Abuja – Kaduna Dual Carriageway.

This was disclosed in a statement issued by the Director, Press and Public Relations of the Ministry, Mr. M. A Ahmed on Sunday, October 6, 2024.

Ahmed disclosed that the contractor, Messrs H&M (Nig.) Ltd was mobilised to site on Wednesday, 2nd October, 2024. The contract for the Section I of the Expressway starts at kilometre 0 + 00 (Zuba, FCT) and ends at kilometre 31 + 200 (Tafa, Niger/Kaduna States’ border) with a two (2) weeks completion period.

- Advertisement -

The scope of the contract consists of patching of existing potholes, as well as the reinstatement of critically failed sections of the said alignment. And the approved contract sum is N366 million (Three Hundred and Sixty-Six Million Naira).

Speaking during an inspection tour of the project on Saturday, 5th October, 2024, the Directors, Highways, North Central Zone I, Engr. Mohammed Goni and Special Projects (North), Engr. Olufemi Adetunji urged the contractor to adhere with the terms of the contract, as no extension of the completion period will be entertained.

They described the project as a catalyst to economic growth and a vital artery connecting the Northern and Southern parts of the country. Engr. Goni promised Nigerians that with the successful completion of the contract, the remaining failed parts from Tafa – Kaduna will also be awarded, reiterating the resolve of the present administration to the provision of critical road infrastructure.

The Project Supervisor, H&M (Nig.) Ltd, Mr. Lawrence Emmanuel disclosed that work was ongoing with the cutting and shaping of the failed portions reaching Dikko Junction in Niger State, while the asphalting of the cut points was expected to start on Monday, 7th October, 2024.

While complaining about the high volume of traffic on the road, which was slowing the pace of work, he promised its delivery on the scheduled date.

Also on the inspection visit was the Federal Controller of Works, FCT, Engr. Yakubu Usman, who promised daily inspections and diligent supervision of the project, while it lasts.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Back to top button