TCN Announces Scheduled Outage On Benin-Ajaokuta 330kV Transmission Line

By Sunday Etuka

The Transmission Company of Nigeria (TCN) has alerted the public of a scheduled outage on Benin–Ajaokuta 330kV Transmission Line to facilitate ongoing restringing works at the Ihovbor Power Plant Turn-In/Turn-Out Transmission Substation.

TCN’s General Manager, Public Affairs, Ndidi Mbah, who announced the development in a statement, disclosed that the restringing project which commenced on Friday, 27th February 2026, and would run through Tuesday, 31st March 2026, from 8:00am to 6:00pm daily.

The exercise, according to her, was necessary to enable TCN’s contractor to continue the restringing works on the 330kV transmission line connected to the Ihovbor Power Plant.

- Advertisement -

Additionally, she said, the project requires temporary power interruptions because the transmission line crosses major highways along the Benin–Ajaokuta axis.

The GM said the road safety agencies have been duly notified and would be on standby to ensure public safety throughout the construction period.

She explained that the Benin Electricity Distribution Company (BEDC) would be unable to supply electricity to its customers in UNIBEN, Oluku, Egba, and Ihovbor environs for up to 10 hours each day during the construction period.

“Please note that restringing activities will be suspended daily at 6:00pm, after which the affected feeders will be restored. This means that BEDC will be able to off-take electricity to the above-mentioned areas from 6:00pm until 8:00am the following day,” Mbah added.

TCN apologised for any inconvenience this may cause and assured all affected customers that full bulk power supply would be restored to the DisCo upon completion of the project.