Power

Power: FG Commissions New 120MVA Transmission Substation In Gombe

By Sunday Etuka

The Federal Government has commissioned a new 2x60MVA transmission substation in Billiri, Gombe State, and also inaugurated a 300MVA and a 100MVA power transformer at the Gombe Transmission Substation.

The Minister of Power, Joseph Tegbe, performed the commissioning on Thursday, 19th November, 2026.

Speaking at the Billiri substation, Tegbe said the 120MVA facility would strengthen the economic foundation of host communities, stimulate businesses, attract investment and create jobs.

- Advertisement -

He said the project was designed to tackle longstanding electricity infrastructure challenges that have held back the productive potential of Billiri, Numan and neighbouring communities, adding that reliable power was critical to unlocking their economic opportunities.

Tegbe described the investment as part of President Bola Tinubu’s commitment to strengthening critical transmission infrastructure, so that no community is denied the chance to prosper because of inadequate electricity supply.

According to him, the Billiri facility has an installed capacity of 120MVA, equal to about 96 megawatts, made up of two 60MVA transformers connected to the existing Gombe to Zabana to Yola transmission line. It is expected to boost supply within the Jos Electricity Distribution Company franchise area.

The minister said improved electricity would support businesses and other productive activities. He urged residents to guard the facility, warning that vandalism could erode its benefits.

“These equipment you have here are your assets. They’ve been built for you and for your use. So I make a great appeal to you. You must take care of these facilities. Keep these facilities safe,” he told the community.

He commended the Gombe State Government for partnering with the Federal Government, saying Governor Muhammadu Inuwa Yahaya’s commitment had created an enabling environment for investment.

At the Gombe Transmission Substation, the Federal Government doubled transmission capacity from 300MVA to 600MVA.

The upgrade is expected to improve electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East.

The work involved installing an additional 300MVA, 330/132kV transformer, which lifts capacity at the 330kV level to 600MVA.

An existing 30MVA transformer was also replaced with a 100MVA, 132/33kV unit, raising downstream capacity to 220MVA, or 176 megawatts.

Tegbe said the upgrade would accommodate rising demand, with benefits reaching other parts of the North-East, including Yobe State.

Earlier, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, said demand in Gombe and the areas served by the station had outgrown its previous configuration.

He said the Transmission Company of Nigeria awarded the project in June 2021 and completed it in June 2026.

“The new transformers provide our system operators with greater operational flexibility,” Abdulaziz said. “At the 330kV level, the station now has increased capacity to wheel more power onward. At the 132/33kV level, the larger unit provides the Jos Electricity Distribution Company with increased offtake capacity to serve customers in Gombe.”