FG Plans Free Trial Rides On Kaduna-Kano Rail

By Stella Enenche, Abuja

The Federal Government is considering a three-month trial run of the Kaduna-Kano railway line, with plans to offer passengers free rides during the period, subject to President Bola Tinubu’s approval.

The Permanent Secretary of the Ministry of Transportation, Engr. Funso Adebiyi, disclosed this on Thursday during an inspection of the corridor ahead of its planned December commissioning.

He said the trial would test the structural integrity and operational readiness of the railway before the Nigerian Railway Corporation (NRC) takes over its management.

- Advertisement -

Adebiyi said concerns raised during previous inspections, particularly passenger safety, lighting and maintenance, had been addressed.

He disclosed that toughened glass in passenger areas had been replaced with laminated glass to reduce the risk of injuries in case of breakage.

“The change was necessary because toughened glass could shatter under certain conditions, including exposure to high temperatures or accidents, whereas laminated glass would minimise the danger to passengers,” he said.

He added that the lighting system had been upgraded with bulbs expected to last at least three years.

On maintenance, Adebiyi said the government was providing man lifts and arranging intensive training for NRC engineers.

He added that only personnel who pass the required examinations would be retained for operational duties.

He also confirmed that four lifts had been ordered to improve access for persons with disabilities.

On the outstanding Jaji-Kaduna section, he said security and land acquisition challenges had necessitated the construction of a bridge, which was nearing completion.

He projected that the remaining section would be completed within four to six months.

Adebiyi further disclosed that construction of the Ibadan-Osogbo-Ilorin-Minna railway corridor would be flagged off within two months, while the proposed Itakpe-Abuja extension was awaiting presidential approval.

The Director-General of the Debt Management Office, Patience Oniha, said the inspection was part of efforts to monitor government-funded capital projects.

She said the railway would stimulate economic activities along the corridor, creating opportunities for traders, businesses and small-scale entrepreneurs.

A representative of the contractor, China Civil Engineering Construction Corporation, Mark Xu, assured that work would continue towards meeting the December commissioning deadline.