Transmission Company of Nigeria (TCN) has completed reconstruction of three collapsed 132kV transmission towers and restored Karu-Keffi-Akwanga transmission line.
The company said reconstruction of towers T78, T79 and T80 was completed at 5:31 pm on Wednesday October 28 2026, restoring transmission pathways serving 132/33kV Keffi and Akwanga transmission stations.
TCN said the towers collapsed on October 7 2026 following heavy rainfall and strong winds and that maintenance crew worked diligently to reconstruct them and restore the affected line.
Management said TCN remains committed to maintaining and strengthening transmission infrastructure to ensure reliable and efficient transmission of bulk electricity across the country.